Oracle Primavera Cloud Help (2024)

Rules of credit can be used when tracking progress on scope assignments. A rule is defined by its milestones and their percentage complete. These rules are used when contracts require certain conditions to be met before a payment is made. The rules are also used when it is necessary to track progress of an assignment at a more detailed level or when there are specific steps that need to be completed to satisfy the scope assignment.

The rules are configurable to meet the needs of the contract or general project statusing requirements. In some cases, it is necessary to track the percentage complete for each milestone. In other cases, it is only important to track whether the milestone is complete.

A rule of credit is set at the scope assignment level when the work package is set to measure progress by Milestone Percent Complete. The milestones defined for the rule of credit are used to show progress.

Rules of credit are typically defined by project managers and cost controls engineers.


Oracle Primavera Cloud Help (2024)

FAQs

What is the difference between Primavera P6 and Primavera cloud? ›

In P6, you used the enterprise project structure (EPS) to organize and group projects according to your organization's preferred structure, such as company division, phase, geography, or project size. In Primavera Cloud, you'll use workspaces to group and organize projects in a hierarchy.

What are the benefits of Primavera cloud? ›

These tools provide a framework that improves efficiency, collaboration and accuracy. In addition, Oracle Primavera Cloud services allow for better management of budgets, assessing risks, and reducing misunderstandings between stakeholders and project teams.

What is the difference between flag and milestone activity? ›

Milestone and Flag are both events related to activities in Primavera. Their core difference is that while you can update a Milestone manually, you cannot do the same with a Flag. Additionally, Flags are used to track the logic of main events, while Milestones mark points in time.

What is the critical path in Primavera P6? ›

Critical path activities are project tasks that must start and finish on time to ensure that a project ends on schedule. A delay in any critical path activity will delay completion of the project, unless the project plan can be adjusted so that successor tasks finish more quickly than planned.

Is Primavera better than MS project? ›

Both Primavera and Microsoft Project have strong reporting capabilities. However, Microsoft Project provides a wider range of reporting options, including Gantt charts, PERT charts, and resource histograms. Primavera has a more complex interface compared to Microsoft Project, which has a more user-friendly interface.

Why Oracle Primavera Cloud? ›

Oracle Primavera Cloud brings together office and field teams, synchronizing schedules and resources and empowering the thousands of decisions that engineering and construction professionals make every day on projects all over the world. See how connected scheduling helps reshape project delivery.

What are the three types of milestone? ›

Milestones are used to track progress toward a specific goal or event. There are three types of SAFe milestones: Program Increment (PI), fixed-date, and learning milestones.

What are deliverables vs tasks vs milestones? ›

Tasks—Items that need to be completed. Deliverables—Things that need to be produced (e.g. documents). Milestones—Project deadlines, marking the completion of a phase or stage of a project. Issues—Bugs or items that need to be resolved.

What is the average duration of a milestone activity? ›

They have zero duration because they symbolize an achievement, or a point of time in a project.

What is the longest path in Primavera? ›

And in case we've forgotten, Oracle Primavera defines 'Longest Path' as the string of directly related activities that comprise the longest path from the data date to the last activity in the schedule. It calculates this via a process that follows driving relationships through the project.

What is a float in primavera? ›

In project management, float is a term that refers to the number of days that an activity can be delayed before affecting the next activity in the schedule or the project as a whole. Activities with float are known as non-critical activities, as they have some room for delay, if necessary.

What is pert in Primavera P6? ›

Program Evaluation and Review Technique (PERT)

As the name suggests, a Critical Path is a path composed of the critical activities (having the potential of delaying a project) from the start till the completion of the project.

Is Primavera the same as P6? ›

Primavera Cloud offers a variety of enhancements over P6. Many P6 concepts, which cannot be directly replicated, can be configured and implemented in various ways in Primavera Cloud.

What is the difference between P6 and OPC? ›

Budgeting. Primavera P6 supports top-down budgeting at the EPS, project and WBS level, while OPC supports top-down budgeting from portfolios to programs to projects. Defining a budget and assigning budget lines are done via CBS codes at the project level in OPC.

Top Articles
Latest Posts
Article information

Author: Fr. Dewey Fisher

Last Updated:

Views: 6720

Rating: 4.1 / 5 (42 voted)

Reviews: 81% of readers found this page helpful

Author information

Name: Fr. Dewey Fisher

Birthday: 1993-03-26

Address: 917 Hyun Views, Rogahnmouth, KY 91013-8827

Phone: +5938540192553

Job: Administration Developer

Hobby: Embroidery, Horseback riding, Juggling, Urban exploration, Skiing, Cycling, Handball

Introduction: My name is Fr. Dewey Fisher, I am a powerful, open, faithful, combative, spotless, faithful, fair person who loves writing and wants to share my knowledge and understanding with you.